Approval monitor

What has been approved? What has not? Why not?

Planning Agent is defined, not live. The seed separates demolition consents, transmission MIDs, battery operation and GW announcements because they are different legal facts.

  • electrical infrastructure

    CopperString Eastern Link

    Transmission, not a data centre. In the project list because it is the principal committed energy fact for Townsville-scale industrial load in the 2030s.

  • planning lodged

    Supernode North BESS (Solquartz)

    Three 260 MW / 8 h batteries. Storage for industrial/silicon, not a compute campus. Announced MW is BESS power, not IT load.

  • operational

    NQ SPARK

    Simulation and HPC facility (~1,100 m²). Proposition B, not Proposition A.

  • operational

    Liddell Battery

    Do not file this as a 500 MW data centre.

  • announced

    Beetaloo Digital — Weddell

    Site exclusivity and GW-scale statements. Announced ≠ approved ≠ power secured ≠ financed.

  • operational

    NEXTDC D1 Darwin

    Up to 7 MW IT. Not Weddell.

  • operational

    Vocus Darwin–Jakarta–Singapore Cable

    Cable, not a data centre. In the project list because it is the principal fibre fact for Darwin.

  • operational

    NEXTDC PH1 Port Hedland

    1.5 MW planned IT. Cyclone-rated edge. Not hyperscale.

  • operational

    Vocus Horizon

    2,000 km Perth–Port Hedland fibre. Not a data centre.

  • construction

    Qenos Botany demolition and remediation

    Enabling works for a future industrial use. Not a data-centre project.

  • construction

    Qenos Altona make-safe and demolition

    Evidenced future use in local reporting is warehousing.