Australia firstSentinel-2 mosaic liveOpen-Meteo liveGrid adapter offAnnounced ≠ deliverable

operational

NQ SPARK

Simulation and HPC facility (~1,100 m²). Proposition B, not Proposition A.

LIVEHigh confidence
Announced MW
Power secured MW
Developer / operator
JCU / Townsville City Council / NQ SPARK
Energisation
2026Permanent premises at JCU from 2026 reporting. IT MW not published as a campus figure.

Evidence

  • VerifiedExisting

    NQ SPARK is a $32.2 million simulation and HPC facility now occupying space at JCU's Bebegu Yumba campus, Douglas. It is not a hyperscale campus.

    James Cook University · JCU the new home of NQ Simulation Park · published 2026-05-07 · accessed 2026-09-18

  • High confidenceExisting

    NQ SPARK sits on AARNet and NBN, 3.4 km from Lavarack Barracks and 12 km from Townsville CBD.

    NQ SPARK · Facilities — NQ SPARK · published n/a · accessed 2026-09-18