Qenos Botany demolition and remediation
Enabling works for a future industrial use. Not a data-centre project.
LIVEHigh confidence
- Announced MW
- —
- Power secured MW
- —
- Developer / operator
- ESR / —
- Energisation
- Not dated — Not a compute energisation.
Evidence
- VerifiedExisting
Qenos entered voluntary administration on 17 April 2024. ESR, through LAOP, proposed a DOCA. Demolition DA for stages 1 and 2 was approved by Bayside Council in May 2025.
ESR / Botany Industrial Park · Botany Industrial Park community update July 2025 · published 2025-07 · accessed 2026-09-18
- High confidenceExisting
Environmental investigations identified chlorinated hydrocarbons, petroleum hydrocarbons, PFAS and asbestos in soils at the former Qenos Botany landholding.
Botany Industrial Park · Preparing for remediation works at former Qenos landholdings · published 2025-10-21 · accessed 2026-09-18